Click here
Sarens
USA
Close
SARENS
IN THE USA

Sarens entered US Heavy lift and heavy haul space in 2009 by acquiring Rigging International, a company based in California. We officialy changed the name to Sarens USA, INC. in 2012.

Sarens USA, INC has offices in Houston from where we cover the Gulf area, in Montana from where we cover the Midwest, and in Rowesville from where we cover the East coast.

SERVICES

We provide Engineered Heavy Lifting Services

Heavy Lifting

  • We provide Project-based heavy lift services
  • Turnaround maintenance
  • Installation of turbines & generators
  • Erection of steel structures
  • Erection of heat exchangers
  • Installation of mechanical equipment, drums, casing / inlet ducts, vessels, pumps

Heavy Transport Services

  • Out of Gauge and abnormal load transport
  • Project based heavy transport
  • Rental of specialized transport equipment
  • Factory-to-Foundation

Decomissioning and Dismantling Services

Rental Services

  • We provide bare lease as well as operated rentals services
  • Skidding & jacking

OUR
MARKETS

  • New nuclear plant construction
  • Operating nuclear plant
  • Small Modular Reactor (SMR)
  • Decommissioning
  • Department of Energy (DOE)
  • Government
  • Thermal power plants
  • Oil & Gas
  • Petrochemical
  • Major civil projects including:
    • Airports
    • Bridges
    • Stadia
    • Ports & yards
    • Oversized heavy haul

EQUIPMENT

  • Hydraulic cranes
  • Cranes ranging from 90T to 3200T
  • Hydraulic jacks
  • Strand jacks
  • Self Propelled Modular Trailers
  • Semi trailers
  • Out of Gauge transport

OFFICES

Houston, Texas (Office & Yard)
10855 John Ralston Rd
Houston, TX 77044
Tel: 832 536 3669
Fax: 832 615 2678

Missoula, Montana (Office)
7168 Expressway
Missoula, MT 59808
Tel: 406 543 4427

Rowesville, South Carolina (Office & Yard)
122 River Dr
Rowesville, SC 29133
Tel: 832 714 0176

Sorrento LA (Yard)
9204-A Highway 61
Sorrento, LA 70778
Tel: 225 450 7027

Sales
info.us@sarens.com

Accounts
ap.us@sarens.com

Victory Boogie Woogie Tunnel Project in the Netherlands
Shaping tomorrow's infrastructure, lift by lift.
15
August 2018

When Sarens helped transport and lift a tunnel boring machine for the Rotterdamsebaan's Victory Boogie Woogie tunnel, crane driver Peter Schot said, "I love to work on projects like the Rotterdamsebaan. You participate in something you're going to use yourself. When I drive through the tunnel with my family, I can proudly say that I worked on it." 

The tunnel is being built in The Hague, and the boring machine has an important job: drilling 10-20 metres of tunnel per day, it will carve out two 1.640-metre long tunnel tubes over the next several months. 

Sarens worked with client Combinatie Rotterdamsebaan to handle the transport and lift operation for the machine, including the back-up train. To do it, the Sarens team used the following equipment:  

  • LR1350-1 crawler crane
  • LTM1400-7.1 mobile crane
  • LTM1130-5.1 mobile crane
  • AC700 all terrain crane
  • SPMT 

The tunnel boring machine measures 80 metres long and has a diameter of just over 11 metres. Transporting it from Germany to the project site at Den Haag required over 50 trailers containing loads up to 130 tonnes and measuring 5.7 metres wide by 4.4 metres high. 

Once it was delivered, crews began assembling the machine as well as the crawler crane to be used for the lift. Because the area available for crane operation was limited, Sarens chose to use the LR1350-1 crane in an LDB configuration for its capacity and ability to manoeuvre in the narrow space. 

Due to the narrow working conditions, some parts of the tunnel boring machine had to be assembled close to the launching shaft and then transported via SPMTs to the crawler crane for the lift. The crew also used a second mobile crane for the installation of the back-up trailer. 

Working with a maximum of 10 crew members at a time, Sarens performed major lifts for the 130-tonne cutting wheel, 120-tonne steel cylinder, and 70-tonne pump station, which required two mobile cranes working in tandem. 

Sarens is proud to have been a part of this project and looks forward to the completion of the tunnel and opening of the roadway. Please watch this  time-lapse video of the operation to see how it's all coming together!