Sarens entered US Heavy lift and heavy haul space in 2009 by acquiring Rigging International, a company based in California. We officialy changed the name to Sarens USA, INC. in 2012.
Sarens USA, INC has offices in Houston from where we cover the Gulf area, in Wisconsin from where we cover the Midwest, and in Rowesville from where we cover the East coast.
We provide Engineered Heavy Lifting Services
Heavy Lifting
Heavy Transport Services
Decomissioning and Dismantling Services
Rental Services
SARENS IN THE USA
10855 John Ralston Rd
Houston, Texas 77044
+ 1 832 536 3669
+ 1 832 615 2678
info.USA@sarens.com
SARENS IN THE USA
9204-A Highway 61
Sorrento, Louisiana 70778
+ 1 225 450 7027info.USA@sarens.com
SARENS IN THE USA
15095 W 42nd St.
Odessa, TX 79764
832-493-5741info.USA@sarens.com
Sarens USA – East
75 N. Haddon Ave Suite 101
Haddonfield, NJ, 08033
+1 856 503 2121
Paul.Fuerneisen@Sarens.com
SARENS USA OFFSHORE WIND DIVISION
75 N. Haddon Ave Suite 101
Haddonfield, NJ 08033
856-873-0473
Paul.Fuerneisen@Sarens.com
SARENS NUCLEAR & INDUSTRIAL SERVICES
1430 South Goodland Road
Hartford, WI 53027
+ 1 414 299 0858
nuclear@sarens.com
Sarens was commissioned to install heavy modules for Lukoil’s oil platform in Astrakhan, Russia. As part of the project the team had to install modules of a drilling rig and other equipment on the top-side oil platform of Lukoil.
The CC 6800-1 in configuration SSL/LSL 114m was deployed with a 240T superlift owing to the heavy weight modules being lifted to a height of around 100m.
CC6800-1 was delivered from Tobolsk and some parts were mobilised from Atyrau, Kazakhstan. Mobilisation took 20 days and the assembly was completed in 10 days. According to the Project Manager, Alexey Budanov, “The construction site was very congested as several contractors were working simultaneously on the site. Our choice of the crane with the superlift ensured smooth lift and installation in the given space with maximum reach.”
The team lifted the middle module of the drilling rig weighing 175T and the upper module weighing 75T along with other smaller sections and safely installed at a maximum height of total 100m.