Sarens entered US Heavy lift and heavy haul space in 2009 by acquiring Rigging International, a company based in California. We officialy changed the name to Sarens USA, INC. in 2012.
Sarens USA, INC has offices in Houston from where we cover the Gulf area, in Wisconsin from where we cover the Midwest, and in Rowesville from where we cover the East coast.
We provide Engineered Heavy Lifting Services
Heavy Lifting
Heavy Transport Services
Decomissioning and Dismantling Services
Rental Services
SARENS IN THE USA
10855 John Ralston Rd
Houston, Texas 77044
+ 1 832 536 3669
+ 1 832 615 2678
info.USA@sarens.com
SARENS IN THE USA
9204-A Highway 61
Sorrento, Louisiana 70778
+ 1 225 450 7027info.USA@sarens.com
SARENS IN THE USA
15095 W 42nd St.
Odessa, TX 79764
832-493-5741info.USA@sarens.com
Sarens USA – East
75 N. Haddon Ave Suite 101
Haddonfield, NJ, 08033
+1 856 503 2121
Paul.Fuerneisen@Sarens.com
SARENS USA OFFSHORE WIND DIVISION
75 N. Haddon Ave Suite 101
Haddonfield, NJ 08033
856-873-0473
Paul.Fuerneisen@Sarens.com
SARENS NUCLEAR & INDUSTRIAL SERVICES
1430 South Goodland Road
Hartford, WI 53027
+ 1 414 299 0858
nuclear@sarens.com
Working for the client, Malaysia Marine and Heavy Engineering Sdn Bhd (MMHE), a wholly-owned subsidiary of Malaysia Marine and Heavy Engineering Holdings Berhad (MHB), Sarens was asked to move, weigh, and jack the CPP topside module for Kasawari Gas Development Project in Johor, Malaysia.
The crew used the following equipment:
The CS5000, one of the most advanced jacking system, is used for lifting ultra-heavy modules and structures and has a jacking capacity of 5000T per tower. The team had to fabricate a new part for the CS5000 jacking system to customise it for lifting the CPP topside modules weighing 21000T.
The equipment was sent to site via road and sea transport from Belgium, Egypt, Vietnam, Indonesia, and Malaysia in three months. The CS5000 was set-up in a month underneath topside. With close cooperation between the teams and with the client the set-up was safely completed ahead of schedule.
The shifting of the module was carried out in two phases:
According to the assistant project manager, Ridzuan Jamiran (Operations Manager, Tim Van Hoeydonck) “The most challenging part of the project was the installation and positioning of the jack.” He adds - We had to do it in three steps:
Once the jacking system was positioned under the topside module, it was jacked-up by 7m.
Sarens Assistant Project Manager, Ridzuan Jamiran, says, “We are extremely proud of this amazing job where we used eight sets of the CS5000 jacking system and a combination of SPMTs to jack the 21000T topside module. We are thankful to all the stakeholders involved with the project for successfully and safely completing the project.”