Click here
Sarens
USA
Close
SARENS
IN THE USA

Sarens entered US Heavy lift and heavy haul space in 2009 by acquiring Rigging International, a company based in California. We officialy changed the name to Sarens USA, INC. in 2012.

Sarens USA, INC has offices in Houston from where we cover the Gulf area, in Wisconsin from where we cover the Midwest, and in Rowesville from where we cover the East coast.

SERVICES

We provide Engineered Heavy Lifting Services

Heavy Lifting

  • We provide Project-based heavy lift services
  • Turnaround maintenance
  • Installation of turbines & generators
  • Erection of steel structures
  • Erection of heat exchangers
  • Installation of mechanical equipment, drums, casing / inlet ducts, vessels, pumps

Heavy Transport Services

  • Out of Gauge and abnormal load transport
  • Project based heavy transport
  • Rental of specialized transport equipment
  • Factory-to-Foundation

Decomissioning and Dismantling Services

Rental Services

  • We provide bare lease as well as operated rentals services
  • Skidding & jacking

OUR
MARKETS

  • New nuclear plant construction
  • Operating nuclear plant
  • Small Modular Reactor (SMR)
  • Decommissioning
  • Department of Energy (DOE)
  • Government
  • Thermal power plants
  • Oil & Gas
  • Petrochemical
  • Major civil projects including:
    • Airports
    • Bridges
    • Stadia
    • Ports & yards
    • Oversized heavy haul

EQUIPMENT

  • Hydraulic cranes
  • Cranes ranging from 90T to 3200T
  • Hydraulic jacks
  • Strand jacks
  • Self Propelled Modular Trailers
  • Semi trailers
  • Out of Gauge transport

OFFICES

SARENS IN THE USA
10855 John Ralston Rd
Houston, Texas 77044
+ 1 832 536 3669
+ 1 832 615 2678
info.USA@sarens.com

SARENS IN THE USA
9204-A Highway 61
Sorrento, Louisiana 70778
+ 1 225 450 7027info.USA@sarens.com

SARENS IN THE USA
15095 W 42nd St.
Odessa, TX 79764
832-493-5741info.USA@sarens.com

Sarens USA – East
75 N. Haddon Ave Suite 101
Haddonfield, NJ, 08033
+1 856 503 2121
Paul.Fuerneisen@Sarens.com

SARENS USA OFFSHORE WIND DIVISION
75 N. Haddon Ave Suite 101
Haddonfield, NJ 08033
856-873-0473
Paul.Fuerneisen@Sarens.com

SARENS NUCLEAR & INDUSTRIAL SERVICES
1430 South Goodland Road
Hartford, WI 53027
+ 1 414 299 0858
nuclear@sarens.com

Darlington Bridge Project: Sarens Installs 3 More Bridge Sections in Adelaide
With the $620 million Darlington Bridge project nearing completion, Sarens was on site to install three more bridge sections from August through November of 2018.
9
April 2019

With the $620 million Darlington Bridge project nearing completion, Sarens was on site to install three more bridge sections from August through November of 2018. This phase of the project built on  Sarens' earlier success installing a 3.000-tonne bridge section in 2017. For this operation, SPMTs would again transport and install massive bridge portions in Darlington, Adelaide: bridge BR02, bridge BR03, and bridge BR14-N.   

Up until now, bridge moves of this size were unheard of in Australia, so Sarens' early involvement in the planning process was key. From the very beginning, Sarens provided ABC (accelerated bridge construction) workshops and use of SPMTs for bridge construction to client Gateway South and end client DPTI (Department of Planning, Transport and Infrastructure South Australia). 

Planning for Challenges 

Sarens engineers had to plan for some special challenges during this operation. First, the travel path for bridges BR02 and BR03 had a significant change in transverse gradient, resulting in an insufficient SPMT stroke. To remedy this, Sarens' engineering team introduced the CS250 jacking system on the two outermost SPMT units. 

Tim Devoldere, operations manager for Sarens Australia, explains the solution in layman's terms: "Imagine four people carrying a log on their shoulders. When going through a dip, the people in the middle will have to raise their arms in order to keep supporting the log. If the dip becomes too deep, their arms might not be long enough. That's what happens when SPMTs run out of stroke. By introducing the CS250 jacking system, we gave these people longer arms." 

Another challenge was the huge curvature of the 14-N bridge section. To account for this, SPMT units had to be perfectly aligned perpendicular to the radius of the curve. 

Preparing Equipment 

To install the three bridge sections, Sarens deployed 132 axle lines SPMT, six PPUs, eight CS250 climbing systems, and auxiliary equipment including forklifts, an aerial working platform, and 110-tonne all terrain crane. 

Within a span of 12 weeks, equipment was mobilised from all over the world, including Belgium, Vietnam, and Australia. However, in some cases equipment was held at port for two months due to strict Australian quarantine regulations and inspection requirements. 

Executing Operations 

Once the equipment was ready, operations commenced along a busy highway through Adelaide, and the 16-member crew worked on a tight schedule to minimise traffic interference. For each bridge, the road closure allowance was 56 hours, though the actual duration of transport varied from 16-22 hours. 

Working in August, September, and November, the crew installed the following bridge segments: 

  • BR02, weighing 3.000 tonnes and measuring 178 metres long.
  • BR03, weighing 2.800 tonnes and measuring 182 metres long.
  • BR14-N,weighing 3.100 tonnes and measuring 195 metres long. 

The crew used 132 axle lines SPMT and six power packs to install each of the bridges. Bridges BR02 and BR03 also required the use of eight CS250 jacking systems. 

"The SPMT transport and installation of bridges of this size was a first in Australia," says Tim Devoldere. "The successful completion of this project is a result of the early involvement of our KAM Brett Beveridge at tender stage, the detailed engineering led by Peter Keyen in head office, and the excellent cooperation between all business units and highly-skilled multinational crew involved during preparation, logistics, and actual execution." 

Nigel Hird, project manager at Gateway South says, "The success of these incredibly complicated installations is a testament to Sarens' commitment and capabilities. The staggering amount of engineering, planning, and then seamless execution of these works received the highest levels of praise from all parties involved." 

Sarens is proud to have been a part of this tremendous project, and would like to thank everyone who has been involved from start to finish.