Sarens Accurately Jacks-up 1100T Structure of the Danieli Ship Grab Unloader
Sarens jacks-up the upper structure of the Danieli Ship Grab Unloader (SGU) in Bilbao, Spain
12
July 2018

In the harbor of Bilbao, Sarens was contracted by URSSA Steel Constructions to jack-up the upper structure of a Ship Grab Unloader weighing 1100T. The structure was manufactured on the bottom sill beams of the SGU, 5m above ground level, and lifted more than 50m until its final position.

To undertake the operation, our team deployed eight 200T lifting strandjacks and four 150T tie-back strandjacks. The equipment was transported from the Belgium yard in two days and took around 2 weeks for assembly.

URSSA has commissioned similar type of jack-ups in the past using more than 16 strandjacks, but Sarens provided the client with a technically superior and a commercially viable solution by deploying only 12 strandjacks.

4 pairs of 200T strandjacks were installed on top of each SGU leg and 4 single tie back strandjacks were installed at the bottom part of those same legs. The 1100T structure was lifted around 50m and placed onto its final position. Once placed, our lifting pair of strandjacks accurately adjusted the structure after which a number of bolts were adjusted between the upper structure and its 4 legs.

According to Sarens KAM, Technical solutions, José Mª Martínez Gutiérrez, "It was a very nice and smooth jack up and the client was happy about the safe lift performed by our team within designated time."