Sarens is proud to have played a key role in the largest shutdown campaign ever undertaken at Hyosung Chemicals Plants in Vietnam. This project highlights our ability to deliver world-class heavy lifting solutions for complex industrial operations.
The project required exceptional planning and execution to meet the client’s ambitious goals. Sarens deployed some of the most powerful cranes in its fleet, including the XCMG XLC 22000 (1,700T), Demag CC6800 (1,250T), Sany SCC4500A (450T), and Demag CC1500 (300T). These machines were instrumental in handling the most challenging lifts, such as heat exchangers weighing 340T lifted to a height of 44 meters. At the helm, our Project Manager Huynh Nhat Truong.
Compared to a 2023 project at the same site, this year’s operation was significantly larger in scale and complexity. Sarens rose to the challenge, ensuring safe and efficient execution throughout the project and reinforcing its position as a trusted partner for industrial giants worldwide.