Stadium Monterrey
Sarens is executing heavy lifting works for the construction of a soccer stadium in Monterrey City.
4
September 2013

Sarens' involvement included full engineering, design and lifting procedures for the installation of the roof support structures. The lifting of these 60t structures at 50m height was accomplished using a CC 2800, assisted by a LR 1400. Sarens' scope also involved site supervision and rigging personnel for the duration of the contract. The LR 1400 was on site from March 2013 until December 2013 and the CC 2800 is expected to finish on time by the end of March 2014. The finished stadium will be able to house over 50,000 soccer fans.