Sarens has completed the lifting and installation of combined stacker/reclaimer components for the NCIG coal export terminal expansion Phase 2. This notably included lifting the Slewdeck (300t) and a tandem lift of the stacker/reclaimer boom (63m - 250t).
The completion of these activities has enabled the initial phase commissioning of the export terminal expansion to commence.