Koniambo
12
July 2011

Scope: Load out, load in and installation of modules
Turnover: $ 68.600.000
Year of completion: 06/2012
Duration: 22 months
Owner: Technip/Hatch & Koniambo Nickel
Location: Koniambo, New Caledonia
Peak of personnel: 130
Equipment:

  • CC8800-1
  • 2 x CC2800-1
  • 2 x LR1400/2
  • LR1350/1 LN
  • LR1350/1 S
  • LR1300
  • SARtower
  • 35 telescopic cranes up to 150 tons
  • 350 axle lines SPMT's

Flyer Koniambo