Click here
Sarens
USA
Close
SARENS
IN THE USA

Sarens entered US Heavy lift and heavy haul space in 2009 by acquiring Rigging International, a company based in California. We officialy changed the name to Sarens USA, INC. in 2012.

Sarens USA, INC has offices in Houston from where we cover the Gulf area, in Montana from where we cover the Midwest, and in Rowesville from where we cover the East coast.

SERVICES

We provide Engineered Heavy Lifting Services

Heavy Lifting

  • We provide Project-based heavy lift services
  • Turnaround maintenance
  • Installation of turbines & generators
  • Erection of steel structures
  • Erection of heat exchangers
  • Installation of mechanical equipment, drums, casing / inlet ducts, vessels, pumps

Heavy Transport Services

  • Out of Gauge and abnormal load transport
  • Project based heavy transport
  • Rental of specialized transport equipment
  • Factory-to-Foundation

Decomissioning and Dismantling Services

Rental Services

  • We provide bare lease as well as operated rentals services
  • Skidding & jacking

OUR
MARKETS

  • New nuclear plant construction
  • Operating nuclear plant
  • Small Modular Reactor (SMR)
  • Decommissioning
  • Department of Energy (DOE)
  • Government
  • Thermal power plants
  • Oil & Gas
  • Petrochemical
  • Major civil projects including:
    • Airports
    • Bridges
    • Stadia
    • Ports & yards
    • Oversized heavy haul

EQUIPMENT

  • Hydraulic cranes
  • Cranes ranging from 90T to 3200T
  • Hydraulic jacks
  • Strand jacks
  • Self Propelled Modular Trailers
  • Semi trailers
  • Out of Gauge transport

OFFICES

Houston, Texas (Office & Yard)
10855 John Ralston Rd
Houston, TX 77044
Tel: 832 536 3669
Fax: 832 615 2678

Missoula, Montana (Office)
7168 Expressway
Missoula, MT 59808
Tel: 406 543 4427

Rowesville, South Carolina (Office & Yard)
122 River Dr
Rowesville, SC 29133
Tel: 832 714 0176

Sorrento LA (Yard)
9204-A Highway 61
Sorrento, LA 70778
Tel: 225 450 7027

Sales
info.us@sarens.com

Accounts
ap.us@sarens.com

Sarens safely performs four of the challenging heavylifts in Egypt
Sarens lifts four absorbers at the West Nile Delta Project successfully completing 10,000 safe working man hours on the project.
7
January 2018

Sarens was contracted by Bechtel Overseas Corporation to perform heavylift operations at BPs West Nile Delta Project over a period of eight months. The initial contract awarded to Sarens was to complete the heavylifting of 10 Cargo. The major task included lifting of four absorbers weighing around 384MT each. This was one of the biggest and crucial heavylift operations ever performed in Egypt. Owing to the team's safe execution of the lifts, Bechtel modified the order to further support it with cranes for general lifting for up to 18 months.  

BP's West Nile Delta onshore gas processing terminal at Idku City, north east of Alexandria, is one of the landmark projects of Egypt. Once completed, the plant will provide processing capacity of around one billion cubic feet of gas per day which equals to approximately one quarter of Egypt's current output. BP awarded the contract to Bechtel, one of the leading service providers specializing in oil and gas fields development, to execute a fast-track engineering, procurement, construction and commissioning program for the West Nile Delta Project.

Sarens' specialized twenty member crew worked during the entire Ramadan period, managing shorter working hours, to successfully lift the four main absorbers at the plant. In the process, the team deployed the following equipment:

  • CC4800
  • LR1350
  • 2 x AC200
  • 2 x LTM1100
  • SCC1500
  • SCC1000
  • RT9130 

CC4800 in Superlift configuration with 48m Main Boom worked as the main crane supported by LR1350 (tailing crane). CC4800 was transported from Thailand and in order to meet the tight schedule rigging tackles were imported via airfreight from Europe, South Africa and Middle East.  

Each of the four absorbers weighing 384MT each, were lifted at a pick-up radius of 18m and a final radius of 16m. The crane did not move during the entire lifting operation, it only boomed-up and slewed to final position. The lifting of the fourth and the final absorber was completed in the first week of July. Prior to the fourth safe and successful lift, Sarens reached 10,000 safe working man hours on the project. 

Congratulating the team on the successful execution of the project, Regional Operations Manager, Steven Coulson remarks, "Using a multinational team, Sarens achieved 4 of the biggest heavylifts ever done in Egypt.  Our team worked hard together to achieve the lifts in a safe and professional manner, especially taking into account the limited working hours available during the Ramadan period."