Antwerp work horses on the move
LOCATION: Antwerp - Belgium
EQUIPMENT USED: Barges Wim & Tom; tugboat Petrus; 72 axle
lines SPMT's
Nothing too heavy,
nothing too high! "Nothing too technically challenging" would
perfectly add to many of our projects, for example the
transportation of two Kalmar cranes (1.250t, 72m high), workhorses
of Antwerp's container terminals.
The major challenge existed in overcoming the different water
levels, since not only a tidal range of approx 6m had to be
overcome, but also a totally different water level at the departure
quay compared to the arrival quay. The only reasonable solution was
to elevate our twin barges Wim & Tom with an extra 1.70m to
ensure smooth cycling from the quay onto the pontoon.
Knowing that maintenance operations always have a severe impact on
terminal activities, Sarens can proudly say that the two transports
have been executed in 6 days instead of the planned 9 days.