Sarens Transports and Installs Twelve 2.65MW Wind Turbines in Vietnam
Sarens installs G114-2.6MW wind turbines at the Dam Nai 2 Wind Farm in Vietnam
24
January 2019

Sarens was commissioned by Siemens Gamesa Renewable Energy to transport and install twelve G114-2.6MW wind turbine generators at the Dam Nai Wind Farm -II in Vietnam. With the second phase added, this wind farm is now the largest of its kind in the Southeast Asian country. The second phase, having a total investment of US$ 60 million, has an average generation of 110 million kWh per year.

Strong winds kick up in this region from around October before which the plant had to be operational. The deadline between the contract's execution and the commissioning of the wind farm was very tight. Our teams were simultaneously facing a challenge of transport option available only during the night for a few hours. To meet the deadline our crew decided to work in two shifts installing two WTG/week.

Sarens deployed the following equipment:

  • For Transportation:
    • Extendable trailers
    • Low bed trailer
    • Hydraulic conventional trailers
  • For Erection:
    • Two 600T Crawler crane
    • 100T Crawler crane
    • 80T Crawler crane
    • 500T hydraulic crane
    • 120T Rough terrain crane
    • 60T Rough terrain crane
    • 32 axle lines of SPMT
    • Two PPU, 3x5T telehandler, flat bed trailer  

The equipment was transported by trailers from the storage yard in Vietnam in five days. Three flatbed trailers, 32 axle-lines of SPMT and 2 PPU at site were deployed for relocation. The equipment was carefully and safely assembled in five days as the hardstand was narrow and unlevelled.

All the tower sections, hub, nacelle, and blades were transported during night due to transport restrictions through public places. Once moved to site, three tower sections, hub, nacelle, three blades each for the twelve WTGs were lifted and installed at a rate of thirty hours/WTG.

Our teams were challenged by heavy rain and strong wind due to which they had to stop the operation in between and then begin installation again to ensure safety. Despite the challenges the installation was successfully competed at a rate of 2WTGs/week. Sarens was awarded and certified for its outstanding performance and lasting contribution of 350,000 safe man-hours without fatality at the Dam Nai wind farm project. 

Watch the video of the operation here!