Lifting of 113t press machine
Location: Tomaszów - Mazowiecki - Poland
Equipment used: AC700; GMK5100
8
February 2012

Sarens unloaded the press machine, which was transported horizontally on a truck, to a vertical position (tailing operation).

For this operation a spreader equipped with 2 sheaves was used. In order to use the boom of our crane, the client especially made a hole in the roof following Sarens' guidelines.

A 100t auxiliary crane was used to put the ballast onto the AC700.

To the client's satisfaction the full operation took only 1 day.